|
| |
| aaa |
|
Bioretention
|
Initial Research at the University of Maryland
|
| In 1996, a two-year study was initiated to quantify the
effectiveness of bioretention in terms of pollutant removal. The study included laboratory
and field experimentation to determine pollutant removal efficiency. The work was
completed through the University of Maryland in
collaboration with the Prince George's
County, Maryland, Department of Environmental Resources, and through support of the National Science Foundation.
This work consisted of laboratory column
studies, box bioretention prototype studies, and field studies of existing
bioretention facilities. It was completed in 1999. Three
manuscripts have been published describing this work.
|
|
Small Box
Studies
A small bioretention study box was constructed 107 cm
long by 76 cm wide with a depth to hold up to 61 cm of materials, plus a 15 cm freeboard.
Two sets of perforated PVC pipes were installed laterally in this box. The upper set had a
diameter of 1.3 cm and was 18 cm below the media surface. The second set contained three
2.2 cm dia. pipes at the bottom of the box. A thin gravel layer was packed around each
pipe. The box was filled with sandy loam soil and it was topped with a 2.5-cm layer of
mulch. Six Creeping juniper plants with branches 13-18 cm long were installed in
this box. |
 |
|
|

|
Large Box
Studies
A large bioretention prototype was 305 cm long by 152
cm wide with a depth to hold up to 91 cm of materials, plus a 15 cm freeboard. This box
had 3 sets of perforated PVC laterals. The upper set was 25 cm below the mulch surface,
containing two 2.2 cm diameter pipes. Three 2.2 dia. laterals placed 56 cm below the
surface made up the middle set. The lower set was at the bottom of the box; six pipes with
diameters of 3.2 cm were employed. Gravel, soil, and mulch were added, as with the smaller
box. This box was planted with twelve small Creeping juniper plants with branches
13-18 cm long and twelve large Creeping juniper plants having branches up to 38 cm
long. |
|
|
| To
each box prototype, a synthetic runoff was applied at a hydraulic loading of 4.1 cm/hr for
6 hours using a calibrated pump. This flow rate was based on a 1.5 cm total rainfall event
with a 6-hour duration, corresponding to a median annual precipitation event for the
Baltimore-Washington area. With the bioretention area sized at 5% of the drainage area, a
rational method c coefficient of 0.8 is assumed to arrive at the design bioretention
runoff loading. The total volume of runoff applied during a 6-hour cycle was approximately
200 liters for the small prototype and 1000 L to the large system.The synthetic runoff contained µg/L concentrations of lead, copper and zinc, and mg/L concentrations
of phosphorus, ammonia-N, nitrate-N, and organic-N, at pH 7.0.
At selected time intervals, infiltrated water samples were collected
from the lateral ports. The bottom ports were always open; the upper ports were opened
only for sampling. From each experiment samples were collected in polyethylene bottles for
metals and nutrients analysis. After collection, samples were refrigerated until they were
analyzed. Three identical experiments each were performed with the small and with the
large box. Additional experiments were performed under different conditions. |
|
|
| The
bioretention lab studies have been published:
Davis, A.P., Shokouhian, M., Sharma, H. and
Minami, C., “Laboratory Study of Biological Retention (Bioretention) for
Urban Storm Water Management,” Water Environ. Res., 73(1),
5-14 (2001).
All LID Publications
|
|
|
|
Field Studies
|
|
Greenbelt, MD,
1997
The first experiment was
at a facility that was constructed in 1992 at a shopping mall parking lot in Greenbelt,
MD. These bioretention systems were covered with about 5 cm of mulch and held a thick
growth of grasses (90-120 cm tall) mixed with a few shrubs and small trees. A 15-cm
diameter perforated PVC pipe was located at a depth of 114 cm in the facility to collect
infiltrated runoff. The outlet of this pipe opens into a manhole which feeds into a large
storm sewer pipe.
An area within the facility, 2.2 m x 2.2 m, near the manhole
was boxed off with sandbags. Using a calibrated pump and 200-L plastic drums, a
synthetic runoff was dispersed throughout the boxed-off area at a hydraulic loading of 4.1
cm/hr over a six hour duration. The total volume applied was 1000 L.
Fifteen minutes after runoff application, the first flow into
the manhole was observed, indicating a high infiltration rate for this facility.
Initially, the flow was mostly coming from cracks in the manhole concrete around the PVC
pipe, but later flow also occurred through the pipe itself. The surface of the
bioretention area became almost completely wet, but no pooling occurred throughout the
entire application period. Approximately 15 minutes after the termination of the
experiment, the drainage from the PVC pipe slowed; by ˝ hr it was reduced to a trickle,
and by 1 hour, flow was not noticeable.
Samples were collected from the PVC underdrain in plastic
bottles and transported to the University of Maryland Environmental Engineering Laboratory
for analysis.
|

|
|
|
  |
Landover,
MD, 1999
The second experiment was completed June 1999 at a County
facility in Landover, Maryland. This system had been installed about one year earlier,
being retrofit into an existing curbside inlet at a parking island. The media consisted of
50% construction sand, 20-30% leaf mulch, and 20-30% topsoil. A 15-cm T-shaped
underdrain runs the span of the entire facility, branching to the inlet 127 cm below the
facility surface, to allow discharge to freely enter the storm drainage system. Bare mulch
made up most of the surface, with some grasses, bushes, and trees. An area 2.1 m by 2.4 m
was cordoned off for runoff application in the center of the south facility.
Again, synthetic runoff was dispersed throughout the
boxed-off area at a hydraulic loading of 4.1 cm/hr over a six hour duration. The
runoff contained µg/L concentrations of lead,
copper and zinc, and mg/L concentrations of phosphorus, nitrate-N, and organic-N, at pH
7.0.
Flow in this facility did not originate from the underdrain,
but entered through a joint in the storm drain inlet. Artifacts resulting from having to
collect the samples from the storm drain joints, instead of having the runoff exit from
the perforated underdrain are not entirely known.
Infiltration was rapid during the test and ponding of the
applied runoff never occurred. Periodic samples were taken in plastic bottles and
transported to the Environmental Engineering Laboratory.
High concentrations of sodium and chloride were noted in the
effluent, likely from the washout of salt accumulated in the facility from the previous
winter. Also, a significant moderation of water temperature was noted from
infiltration through the facility.
|
|
|
|
| Summary
results from the two field experiments completed in 1997 & 1999 are given in the Table below. The copper and
lead concentrations in the effluent at Greenbelt were less than or very near instrument
detection limits (2 µg/L), giving removals of 97±2% (mean ± 1 standard deviation) and
>95%, respectively. All of the zinc concentrations were below the detection limit
(<25 µg/L), for a removal of >95%. At Landover, total lead was removed significantly, at about 70±23% (16 µg/L
effluent); total copper was removed to a lesser extent (43±11%). Zinc was also reduced
with an average removal of 64±42%. Effluent dissolved zinc averaged 390 µg/L. Both
copper and lead concentrations were significantly reduced by the treatment at Landover,
but not to the extent found at Greenbelt
The total phosphorous removal at Greenbelt was 65±8%.
Effluent phosphorus levels were fairly constant over the sampling period. Removal of TKN
was also constant at about 52±7%. Ammonium removal was excellent, averaging 92±7%; the
mean effluent ammonium concentration was 0.22 mg/L as N. The removal for nitrate was poor,
at only 16±6%. This was not unexpected.
Effluent nutrient concentrations were observed to be below
the input in all cases at Landover. Removal for phosphorus was 87±2%, excellent
removal, with effluent concentrations just above 0.1 mg/L P. This was better than the
removal at Greenbelt. TKN removal was 67±9% and nitrate removal averaged 15±12%. Both
showed some variation with time. These results are both comparable to those found at
Greenbelt. Ammonium was not added to the runoff in the Landover study. In contrast to the
metals, very similar nutrient removal efficiencies were found between the two facilities.
|
|
|
Pollutant Removal Summary Table for Field
Studies
| |
Cu (µg/L) |
Pb (µg/L) |
Zn (µg/L) |
P
(mg/L) |
TKN (mg-N/L) |
NH4+ (mg-N/L) |
NO3- (mg-N/L) |
| Greenbelt Field Study |
Input |
66±32 |
42±35 |
530±72 |
0.52 |
3.5 |
2.6 |
0.33 |
Average ± Std.
Dev. |
2±1 |
<2 |
<25 |
0.18±0.04 |
1.7±0.23 |
0.22±0.18 |
0.67±0.49 |
Range |
<2-4.2 |
<2-4.5 |
<25 |
0.15-0.24 |
1.4-1.9 |
0.08-0.53 |
0.25-0.30 |
Removal % |
97±2 |
>95 |
>95 |
65±8 |
52±7 |
92±7 |
16±6 |
| Landover Field Study |
Input |
120±27 |
54±9.4 |
1100±20 |
0.83 |
6.9±0.81 |
- |
1.3±0.05 |
Average ± Std.
Dev. |
69±9.4 |
16±7 |
390±440 |
0.11±0.02 |
2.3±0.64 |
- |
1.1±0.15 |
Range |
55-85 |
6.7-26 |
120-1400 |
0.10-0.13 |
1.7-3.0 |
- |
0.94-1.2 |
Removal % |
43±11 |
70±23 |
64±42 |
87±2 |
67±9 |
- |
15±12 |
|
|
|
|
| Combining
the effluent data from the two field, one large box, and two small box experiments yields
pollutant removals at several different bioretention media depths. Input chemical
concentrations, pH, and loadings were approximately equal in all cases. This allows direct
comparison of the three different experimental scales and permits specific examination of
the pollutant removal efficiencies as a function of bioretention depth. |
|
|
|
 |
Combined Studies-Lead
A plot showing average lead removals for each depth is shown
to the left. Error bars represent ± the standard deviation for data collected over
the application times. Results show excellent agreement among the various
laboratory experiments. As well, excellent agreement was found between the laboratory box
studies and the Greenbelt field data, even though the materials of design were not the
same. Removals were all greater than 90% and variations were small. Nonetheless, results
from the Landover study did not demonstrate the same degree of metals removal. There
were several differences between the Landover and Greenbelt facilities, including
differences in bioretention media, which could be responsible for the removal efficiency
variations.
Companion studies have illustrated the importance of the
mulch layer for metals uptake/sorption in bioretention. Accordingly, a shallow
bioretention facility with several cm of mulch may be adequate for substantial removal of
heavy metals from storm water runoff.
|
|
|
Combined
Studies-Phosphorus
As expected, the overall scatter of the phosphorus data is
greater than for lead. Nonetheless, very good agreement was noted among the
laboratory data and the two field studies. In fact, the scatter among the various system
scales was well within that exhibited by the three boxes that employed the same media. The
phosphorus removals showed very good agreement among all types of experimentation. Better
removal resulted from deeper bioretention through about 61 cm depth. At this point, the
removal plateaued at about 70-85%. Most soils have a significant capacity to adsorb
phosphorus at neutral pH and adsorption was likely the dominant phosphorus uptake
mechanism.
|
 |
|
|
| All
of these bioretention field results have been published:
Davis, A.P., Shokouhian, M., Sharma, H., Minami, C., and Winogradoff, D.
"Water Quality Improvement through Bioretention: Lead, Copper, and
Zinc," Water Environ. Res., 75(1), 73-82 (2003).
Davis,
A.P., Shokouhian, M., Sharma, H., and Minami, C. “Water Quality
Improvement through Bioretention
Media: Nitrogen and Phosphorus Removal,” Water Environ. Res.,
78(3), 284-293 (2006).
All LID Publications |
|
|
Back to A. Davis Homepage
April 28, 2006
|