aaa

Bioretention

Initial Research at the University of Maryland

Small Box Studies 

A small bioretention study box was constructed 107 cm long by 76 cm wide with a depth to hold up to 61 cm of materials, plus a 15 cm freeboard. Two sets of perforated PVC pipes were installed laterally in this box. The upper set had a diameter of 1.3 cm and was 18 cm below the media surface. The second set contained three 2.2 cm dia. pipes at the bottom of the box. A thin gravel layer was packed around each pipe. The box was filled with sandy loam soil and it was topped with a 2.5-cm layer of mulch. Six Creeping juniper plants with branches 13-18 cm long were installed in this box.

smallbox.jpg (50866 bytes)

biot-5.jpg (22768 bytes)

Large Box Studies

A large bioretention prototype was 305 cm long by 152 cm wide with a depth to hold up to 91 cm of materials, plus a 15 cm freeboard. This box had 3 sets of perforated PVC laterals. The upper set was 25 cm below the mulch surface, containing two 2.2 cm diameter pipes. Three 2.2 dia. laterals placed 56 cm below the surface made up the middle set. The lower set was at the bottom of the box; six pipes with diameters of 3.2 cm were employed. Gravel, soil, and mulch were added, as with the smaller box. This box was planted with twelve small Creeping juniper plants with branches 13-18 cm long and twelve large Creeping juniper plants having branches up to 38 cm long.

To each box prototype, a synthetic runoff was applied at a hydraulic loading of 4.1 cm/hr for 6 hours using a calibrated pump. This flow rate was based on a 1.5 cm total rainfall event with a 6-hour duration, corresponding to a median annual precipitation event for the Baltimore-Washington area. With the bioretention area sized at 5% of the drainage area, a rational method c coefficient of 0.8 is assumed to arrive at the design bioretention runoff loading. The total volume of runoff applied during a 6-hour cycle was approximately 200 liters for the small prototype and 1000 L to the large system.

The synthetic runoff contained µg/L concentrations of lead, copper and zinc, and mg/L concentrations of phosphorus, ammonia-N, nitrate-N, and organic-N, at pH 7.0.

At selected time intervals, infiltrated water samples were collected from the lateral ports. The bottom ports were always open; the upper ports were opened only for sampling. From each experiment samples were collected in polyethylene bottles for metals and nutrients analysis. After collection, samples were refrigerated until they were analyzed. Three identical experiments each were performed with the small and with the large box. Additional experiments were performed under different conditions.

The bioretention lab studies have been published:

Davis, A.P., Shokouhian, M., Sharma, H. and Minami, C., “Laboratory Study of Biological Retention (Bioretention) for Urban Storm Water Management,” Water Environ. Res., 73(1), 5-14 (2001).

 

 

Field Studies

Greenbelt, MD, 1997 

The first experiment was at a facility that was constructed in 1992 at a shopping mall parking lot in Greenbelt, MD. These bioretention systems were covered with about 5 cm of mulch and held a thick growth of grasses (90-120 cm tall) mixed with a few shrubs and small trees. A 15-cm diameter perforated PVC pipe was located at a depth of 114 cm in the facility to collect infiltrated runoff. The outlet of this pipe opens into a manhole which feeds into a large storm sewer pipe.

An area within the facility, 2.2 m x 2.2 m, near the manhole was boxed off with sandbags.  Using a calibrated pump and 200-L plastic drums, a synthetic runoff was dispersed throughout the boxed-off area at a hydraulic loading of 4.1 cm/hr over a six hour duration.  The total volume applied was 1000 L. 

Fifteen minutes after runoff application, the first flow into the manhole was observed, indicating a high infiltration rate for this facility. Initially, the flow was mostly coming from cracks in the manhole concrete around the PVC pipe, but later flow also occurred through the pipe itself. The surface of the bioretention area became almost completely wet, but no pooling occurred throughout the entire application period. Approximately 15 minutes after the termination of the experiment, the drainage from the PVC pipe slowed; by ˝ hr it was reduced to a trickle, and by 1 hour, flow was not noticeable.

Samples were collected from the PVC underdrain in plastic bottles and transported to the University of Maryland Environmental Engineering Laboratory for analysis. 

 

bioret-6.jpg (125914 bytes)

bior-4.jpg (57443 bytes)

biolargo1.jpg (291148 bytes)biolargo2.jpg (135414 bytes)

Landover, MD, 1999

The second experiment was completed June 1999 at a County facility in Landover, Maryland. This system had been installed about one year earlier, being retrofit into an existing curbside inlet at a parking island. The media consisted of 50% construction sand, 20-30% leaf mulch, and 20-30% topsoil.  A 15-cm T-shaped underdrain runs the span of the entire facility, branching to the inlet 127 cm below the facility surface, to allow discharge to freely enter the storm drainage system. Bare mulch made up most of the surface, with some grasses, bushes, and trees. An area 2.1 m by 2.4 m was cordoned off for runoff application in the center of the south facility.

Again, synthetic runoff was dispersed throughout the boxed-off area at a hydraulic loading of 4.1 cm/hr over a six hour duration.  The runoff contained µg/L concentrations of lead, copper and zinc, and mg/L concentrations of phosphorus, nitrate-N, and organic-N, at pH 7.0. 

Flow in this facility did not originate from the underdrain, but entered through a joint in the storm drain inlet. Artifacts resulting from having to collect the samples from the storm drain joints, instead of having the runoff exit from the perforated underdrain are not entirely known.

Infiltration was rapid during the test and ponding of the applied runoff never occurred.  Periodic samples were taken in plastic bottles and transported to the Environmental Engineering Laboratory.

High concentrations of sodium and chloride were noted in the effluent, likely from the washout of salt accumulated in the facility from the previous winter.  Also, a significant moderation of water temperature was noted from infiltration through the facility. 

 

Some of the bioretention field results have been published:

Davis, A.P., Shokouhian, M., Sharma, H., Minami, C., and Winogradoff, D. "Water Quality Improvement through Bioretention: Lead, Copper, and Zinc," Water Environ. Res., 75(1), 73-82 (2003).

 
bior-diagram.jpg (120560 bytes) bigbox.jpg (60604 bytes) bio-p.jpg (55192 bytes) biocolumns1.jpg (31378 bytes)
Bioretention Home

Bioretention Installations

Bioretention Research     Bioretention Results and Publications Ongoing Bioretention Studies
How NOT to do Bioretention Installation Photos

Back to A. Davis Homepage

March 26, 2003